# How to report Ontario EWRB through Portfolio Manager: a step-by-step guide

By [John Kennedy, CEM](https://brickflow.ca/about#john-kennedy), founder of BrickFlow. Facts last checked on October 9, 2026.

## In short

- **Who must report:** Private owners of buildings of 50,000 sq ft or more in Ontario on a [listed property type](https://www.ontario.ca/document/guide-energy-and-water-reporting/list-building-types); public agencies are exempt
- **Deadline:** July 1 each year, for the previous calendar year (January 1 to December 31)
- **How to file:** Through ENERGY STAR Portfolio Manager, by responding to the [ministry's EWRB data request](https://www.ontario.ca/document/guide-energy-and-water-reporting/submit-your-report)
- **What is reported:** Building details, gross floor area, the six-digit EWRB ID, and all energy and water use
- **Verification:** Buildings of 100,000 sq ft or more: a [qualified professional](https://www.ontario.ca/document/guide-energy-and-water-reporting/information-you-need-reporting) verifies the data in the first reporting year and every five years after
- **Public data:** Intensities, ENERGY STAR score and basic identifiers are published on the [Ontario Data Catalogue](https://data.ontario.ca/dataset/energy-and-water-usage-of-large-buildings-in-ontario)

Ontario’s Energy and Water Reporting and Benchmarking program (EWRB) requires owners of large buildings to report a full calendar year of energy and water use to the Ministry of Energy and Mines every year. The rules are set by [Ontario Regulation 506/18](https://www.ontario.ca/laws/regulation/180506) under the Electricity Act, 1998, and the ministry explains them in its [Guide to energy and water reporting](https://www.ontario.ca/document/guide-energy-and-water-reporting). There is no separate EWRB form: you report through ENERGY STAR Portfolio Manager.

This guide is for owners, property managers and consultants who file EWRB reports for commercial, multi-residential, institutional or mixed-use buildings in Ontario. It follows the steps the province describes, in order, and notes where buildings of 100,000 sq ft or more also need verification.

## Does it apply to you?

You must report if you own a building in Ontario, other than as a public agency, and the building meets every criterion in [section 3 of O. Reg. 506/18](https://www.ontario.ca/laws/regulation/180506):

-   Part of it sits on a property whose [Municipal Property Assessment Corporation (MPAC) property code](https://www.mpac.ca/en/PropertyTypes/FindYourPropertyType/Propertycodes) appears in the ministry’s [list of building types](https://www.ontario.ca/document/guide-energy-and-water-reporting/list-building-types). The list covers residential (including condominiums and co-operative housing), office, retail, hotel, entertainment and cultural, commercial condominium, industrial (such as warehousing and distribution centres), institutional (such as schools, hospitals and retirement homes) and other types.
-   Electricity or gas is consumed there, and consumption information is available from a distributor.
-   Its gross floor area is at least 50,000 sq ft.
-   If it is a multi-unit residential building, it contains more than 10 units.

If a building has more than one owner, they are [jointly responsible](https://www.ontario.ca/laws/regulation/180506), and a condominium corporation counts as an owner. Several buildings on one property can be [reported individually or combined](https://www.ontario.ca/document/guide-energy-and-water-reporting/who-needs-report); the ministry calls separate reporting [best practice](https://www.ontario.ca/document/guide-energy-and-water-reporting/what-you-are-required-report).

### Exemptions

[Publicly owned buildings are exempt](https://www.ontario.ca/page/report-energy-water-use-large-buildings). The ministry lists two other kinds of [exemption](https://www.ontario.ca/document/guide-energy-and-water-reporting/who-exempt-reporting):

-   **Ongoing:** at least 50% of the gross floor area is occupied by a public agency; at least 10% functions as a data centre, television studio or trading floor; or at least 10% is used for manufacturing, commercial, agricultural or industrial processing and those operations mainly govern the building’s environmental conditions.
-   **One year:** an owner is insolvent at any time in the year; the property is subject to a tax arrears certificate, power of sale or foreclosure, or a writ of execution; or the building is newly constructed and its occupancy certificate is issued that year.

An exemption is not automatic. You give the ministry written notice using the [EWRB exemption form](https://forms.mgcs.gov.on.ca/en/dataset/033-0041). For a one-year exemption, [section 6 of the regulation](https://www.ontario.ca/laws/regulation/180506) requires that notice at least 60 days before that year’s reporting deadline.

## What you need before you start

-   **A Portfolio Manager account and a building profile.** [Create a free ENERGY STAR Portfolio Manager account](https://portfoliomanager.energystar.gov/pm/signup) if you do not have one, then [set up the property](https://www.energystar.gov/buildings/tools-and-resources/how-set-your-property-portfolio-manager) (steps 1 and 2 below). Ontario’s [Portfolio Manager guide](https://www.ontario.ca/page/submitting-data-through-portfolio-manager-ontarios-energy-and-water-reporting-and-benchmarking) walks through both.
-   **Your EWRB ID.** The ministry assigns each building a [six-digit EWRB ID](https://www.ontario.ca/document/guide-energy-and-water-reporting/information-you-need-reporting). It stays with the building when it is sold. If you do not have it, contact EWRB Support (1-844-274-0689 or [ewrbsupport@ontario.ca](mailto:ewrbsupport@ontario.ca)) with the building’s 15-digit assessment roll number and street address.
-   **A current reporting lead.** Keep your organization’s [EWRB Reporting Lead contact](https://forms.mgcs.gov.on.ca/en/dataset/033-0042) up to date; this is how the ministry sends notices and EWRB IDs.
-   **Gross floor area.** The regulation measures it [between the principal exterior surfaces of the enclosed fixed walls](https://www.ontario.ca/laws/regulation/180506), including common areas and excluding open-air spaces such as parking. Use blueprints, architectural plans or a measurement you can source. If the building has several use types, you also need the [floor area of each use](https://www.ontario.ca/document/guide-energy-and-water-reporting/what-you-are-required-report).
-   **Twelve months of usage for every source.** Electricity, natural gas and water, plus any other fuel the building uses, such as diesel, fuel oil, district energy or wood, for [January 1 to December 31](https://www.ontario.ca/document/guide-energy-and-water-reporting/information-you-need-reporting).
-   **Whole-building data from your utilities.** Under [section 12 of the regulation](https://www.ontario.ca/laws/regulation/180506), when you ask, your electricity, natural gas and water distributors must give you aggregated whole-building consumption, broken down by month where they collect it monthly, either directly or into your Portfolio Manager account. If tenants pay their own utilities, the utility [may ask for proof of your authorization](https://www.ontario.ca/document/guide-energy-and-water-reporting/information-you-need-reporting), usually a letter signed by the owner, the tenant, or both.
-   **A verifier, if verification is due this year** (see [Verification](#verification)).

## Step by step

These steps follow the ministry’s [How to report](https://www.ontario.ca/document/guide-energy-and-water-reporting/how-report) and [Submit your report](https://www.ontario.ca/document/guide-energy-and-water-reporting/submit-your-report) pages. The ministry’s [Portfolio Manager guide](https://www.ontario.ca/page/submitting-data-through-portfolio-manager-ontarios-energy-and-water-reporting-and-benchmarking) has screen-by-screen detail.

1.  **Sign in to Portfolio Manager.** [Log in](https://portfoliomanager.energystar.gov/pm/login) or [register](https://portfoliomanager.energystar.gov/pm/signup). You keep the same account from year to year ([How to report](https://www.ontario.ca/document/guide-energy-and-water-reporting/how-report)).
2.  **Add the property.** If you have not reported before, choose “Add a Property” and enter the name, postal code, size and use types. Use the postal code from the property assessment notice or tax bill. Create one profile for each building you report separately ([How to report](https://www.ontario.ca/document/guide-energy-and-water-reporting/how-report)).
3.  **Add a vacant use if needed.** If more than 10% of the building is vacant, add a separate “Vacant” use type ([How to report](https://www.ontario.ca/document/guide-energy-and-water-reporting/how-report)).
4.  **Enter the EWRB ID.** On the property’s “Details” tab, in the “Standard IDs” panel, select “Ontario EWRB ID” and enter the six-digit ID ([How to report](https://www.ontario.ca/document/guide-energy-and-water-reporting/how-report)).
5.  **Set up meters.** On the “Energy” and “Water” tabs, create a whole-building meter or source for each supply. You do this once; later years reuse the meters ([How to report](https://www.ontario.ca/document/guide-energy-and-water-reporting/how-report)).
6.  **Enter the year’s usage.** Add usage that covers January 1 to December 31 of the reporting year. Billing periods may start before or end after those dates ([How to report](https://www.ontario.ca/document/guide-energy-and-water-reporting/how-report)).
    -   If you do not have whole-building data (for example, you only hold the common area accounts), collect the rest of the consumption from your tenants, or request aggregated whole-building data from each utility. Every utility has its own process; we have compiled [each Ontario utility’s EWRB data request route](https://brickflow.ca/guides/ontario-utility-data-requests).
    -   For the accounts you hold, Green Button is the simplest way to keep the year complete: Ontario’s electricity and natural gas distributors must offer it under [O. Reg. 633/21](https://www.ontario.ca/laws/regulation/r21633). BrickFlow brings in Green Button data for the accounts you authorize and checks each month before it goes to Portfolio Manager.
7.  **Add certifications, if any.** On the “Goals” tab, open the “Sustainable Buildings Checklist”, select the third party and enter the certification details, such as BOMA BEST or LEED ([How to report](https://www.ontario.ca/document/guide-energy-and-water-reporting/how-report)). Certifications appear in the ministry’s [published EWRB data](https://data.ontario.ca/dataset/energy-and-water-usage-of-large-buildings-in-ontario).
8.  **Record verification and identifiers.**
    -   **Verification, if it is due.** After a qualified professional has verified the data, open the property’s “Details” tab and, in the “Verification” section, choose “Add Verification Information”. Enter the verifier’s name, organization, contact details and credentials, the period verified and the date ([Portfolio Manager glossary](https://portfoliomanager.energystar.gov/pm/glossary#VerificationInformation)).
    -   **The ministry’s verification flag.** The ministry’s instructions still ask you to open “Unique identifiers (IDs)” on the “Details” tab, choose “Edit”, and in “Custom ID 3” enter “Data Verification” as the name and “Yes” as the ID if the data was verified ([How to report](https://www.ontario.ca/document/guide-energy-and-water-reporting/how-report)). Until the ministry changes this, do both.
    -   **Best practice: record the building’s identifiers.** Besides the EWRB ID (a Standard ID, step 4), add the MPAC property code and the 15-digit MPAC assessment roll number as [custom IDs](https://portfoliomanager.energystar.gov/pm/glossary#PropertyId) under “Unique identifiers (IDs)”. This is our recommendation, not a ministry requirement: it makes each building easy to match to your tax bill, to MPAC and to the ministry’s records.
9.  **Run the Data Quality Checker.** On the “Summary” tab, choose “Check for Possible Errors” for the reporting year and fix what it flags. Run it again after any change to usage, floor area or meters ([How to report](https://www.ontario.ca/document/guide-energy-and-water-reporting/how-report)).
10.  **Open the EWRB data request.** Go to the year’s EWRB reporting submission data request linked from [Submit your report](https://www.ontario.ca/document/guide-energy-and-water-reporting/submit-your-report). On 9 October 2026 that page links the [EWRB 2025 Reporting Submission](https://portfoliomanager.energystar.gov/pm/reports/dataRequest/accept/38a79725-4748-4371-8c42-d1248f68965d) request; check the page for the link for the year you are filing.
11.  **Select your properties.** Choose every building you are reporting; one submission can include one building, several, or all of them ([Submit your report](https://www.ontario.ca/document/guide-energy-and-water-reporting/submit-your-report)).
12.  **Send the response.** Portfolio Manager adds the request to the [“Data Requests from Others”](https://portfoliomanager.energystar.gov/pm/reports#datarequests) table on the “Reporting” tab. In its “Actions” menu, choose “Send Response”, complete the response form, e-sign it and choose “Send Data” ([Submit your report](https://www.ontario.ca/document/guide-energy-and-water-reporting/submit-your-report); [ENERGY STAR: how to respond to data requests](https://www.energystar.gov/buildings/tools-and-resources/how-respond-data-requests-portfolio-manager)).
13.  **Save the confirmation and archive the year.** Keep the automated Portfolio Manager email; it is your confirmation of submission ([Submit your report](https://www.ontario.ca/document/guide-energy-and-water-reporting/submit-your-report)).

-   File it with everything behind the numbers: the bills or utility data for every meter, the floor area source, the verifier’s sign-off and a copy of the submitted report, in one folder per building and reporting year.
-   Keep the files somewhere shared and backed up, not in one person’s inbox, and name them consistently (for example building, year, document type), so the next person can find them when a verifier, buyer or the ministry asks.
-   BrickFlow can do this for you: it keeps each building’s bills, floor area source and submissions with the reviewed record, year by year.

Do all of this by [July 1](https://www.ontario.ca/page/report-energy-water-use-large-buildings). The regulation requires each calendar year’s information [no later than July 1 in the following year](https://www.ontario.ca/laws/regulation/180506), so 2026 data is due by July 1, 2027.

## Checks before you file

-   Every meter on the property is in Portfolio Manager, including on-site fuels and district energy, not just electricity and natural gas. Alternatively, report the whole building as a single meter for each supply: when you choose the meters to include in the property’s metrics, select “These meter(s) account for the total energy consumption for \[your property\] (a single building)” ([ENERGY STAR: how to get utility data](https://www.energystar.gov/buildings/tools-and-resources/how-get-utility-data-portfolio-manager)).
    -   If one meter holds the combined total of several tenant meters, mark it as an aggregate meter: open the meter, expand “Basic Meter Information” and answer “Yes” to “Is this an Aggregate Meter?” ([Portfolio Manager glossary](https://portfoliomanager.energystar.gov/pm/glossary#AggregateMeters)).
-   Each meter covers all of January 1 to December 31 with no gaps or overlapping bills.
-   Gross floor area matches your source document and last year’s report, or the change is explained (for example an addition).
-   Use types and their floor areas add up to the total, with a “Vacant” use if more than 10% was vacant.
-   The EWRB ID is entered on the right building, especially where one property has several.
-   If verification is due, your verifier has signed off, the “Verification” section on the “Details” tab is complete, and Custom ID 3 says “Data Verification” / “Yes” (step 8).
-   The Data Quality Checker has been run since your last edit.

## Verification

Under [section 10 of O. Reg. 506/18](https://www.ontario.ca/laws/regulation/180506), if your building has a gross floor area of at least 100,000 sq ft, you must have the reported information verified before you submit it:

-   in the first year the building is required to report;
-   in the fifth year after a year in which verification was required; and
-   if you were exempt in a year when verification would have been due, in the first year you are required to report again.

The [ministry’s program page](https://www.ontario.ca/page/report-energy-water-use-large-buildings) summarizes this as the first reporting year and every five years after. For example, under the regulation’s wording, a building first required to report in 2019 would verify in 2019, 2024 and 2029. The Minister can also [ask any reporting owner to verify](https://www.ontario.ca/laws/regulation/180506). For buildings under 100,000 sq ft, verification is [voluntary](https://www.ontario.ca/document/guide-energy-and-water-reporting/information-you-need-reporting).

**Who can verify.** The verifier must hold an [accreditation or certification from a body recognized in Canada or the United States](https://www.ontario.ca/laws/regulation/180506) that qualifies them to verify this information, such as a certified energy manager, building operator, measurement and verification professional or commissioning agent. They may be your own employee. The ministry’s [list of examples](https://www.ontario.ca/document/guide-energy-and-water-reporting/information-you-need-reporting) includes credentials such as Building Operator Certification, Certified Energy Auditor, Certified Measurement and Verification Professional, Certified Building Commissioning Professional, a Condominium Manager licence, Professional Engineers of Ontario and Portfolio Manager certifications. If you would rather not find a verifier yourself, our [verification service](https://brickflow.ca/pricing#services-heading) arranges a qualified professional and records the verification in Portfolio Manager, and Filed for you can then submit the report.

**How it is recorded.** You confirm verification [in Portfolio Manager when you report](https://www.ontario.ca/laws/regulation/180506), in the “Verification” section of the property’s “Details” tab, together with the ministry’s Custom ID 3 flag, as in step 8 above. Neither the regulation nor the ministry’s pages prescribe a verification report format, so agree with your verifier what they will check and what record you will keep. For how verification differs from internal review and from assurance, see [Data verification and assurance](https://brickflow.ca/guides/data-verification-and-assurance).

## After you file

-   **Keep the confirmation email** with the bills, floor area source and verifier’s sign-off for that year.
-   **Resubmit if anything changes.** If you change relevant information after submitting, the ministry says you [must resubmit](https://www.ontario.ca/document/guide-energy-and-water-reporting/submit-your-report).
-   **Expect publication.** The ministry publishes building data on the [Ontario Data Catalogue](https://data.ontario.ca/dataset/energy-and-water-usage-of-large-buildings-in-ontario): city, first three characters of the postal code, EWRB ID, property use types, third-party certifications, energy and water use intensities, greenhouse gas intensity and ENERGY STAR score. It does not publish a building’s total energy or water use, total emissions, gross floor area, occupancy, notes or the owner’s name ([How EWRB uses building data](https://www.ontario.ca/document/guide-energy-and-water-reporting/how-ewrb-uses-building-data)).
-   **In Toronto, report to the City as well.** Toronto buildings of 50,000 sq ft or more [also report to the City](https://www.ontario.ca/page/report-energy-water-use-large-buildings), through Portfolio Manager. See [our Toronto guide](https://brickflow.ca/guides/toronto-energy-water-reporting).
-   **Questions:** EWRB Support, 1-844-274-0689 or [ewrbsupport@ontario.ca](mailto:ewrbsupport@ontario.ca) ([program page](https://www.ontario.ca/page/report-energy-water-use-large-buildings)).

## Common mistakes

-   **Floor area from the wrong source.** Leasable area, a marketing figure or an old appraisal is not gross floor area as the regulation defines it. A figure that changes from year to year without a physical change will distort your intensities.
-   **Missing or overlapping months.** A missing bill, a meter swap or a final bill from a closed account leaves a gap; a re-issued bill entered twice doubles a month. Both show up in the published intensity.
-   **Leaving out tenant-paid utilities.** The report covers the [entire building](https://www.ontario.ca/document/guide-energy-and-water-reporting/information-you-need-reporting), not just the owner’s accounts. Request whole-building data from the utility, with the owner’s authorization if needed.
-   **Unit errors.** Natural gas in m³ entered as GJ, kWh entered as MWh, or water in litres entered as m³ makes a building look many times better or worse than it is. Check the unit on each meter against the bill.
-   **Duplicate meters.** The same supply entered twice, once as a whole-building aggregate from the utility and again from individual bills, double-counts usage. Decide on one source per supply.
-   **Missing fuels.** Diesel for generators, fuel oil, propane and district energy are easy to forget because they do not arrive on a monthly utility bill.
-   **Wrong building, wrong ID.** On multi-building properties, check that each profile carries its own EWRB ID and only its own meters.
-   **Forgetting the verification year.** Buildings of 100,000 sq ft or more need verification on the regulation’s cycle; leave time to engage a verifier before July 1.
-   **Not resubmitting after a correction.** Fixing data in Portfolio Manager after you submit does not update the ministry’s copy until you resubmit.

## How BrickFlow helps

BrickFlow keeps [one reviewed record per building](https://brickflow.ca/how-it-works): floor area with its source, every meter, and twelve months of usage brought in from Green Button data and the bills and files you provide. Our own review flags gaps, overlaps, unit errors and duplicate meters before the data reaches Portfolio Manager, and keeps the documents a verifier will ask for in one place; it does not replace the verification the regulation requires.

## Sources

1.  [Report your building's energy and water use (Ontario)](https://www.ontario.ca/page/report-energy-water-use-large-buildings)
2.  [O. Reg. 506/18: Reporting of energy consumption and water use (e-Laws)](https://www.ontario.ca/laws/regulation/180506)
3.  [Guide to energy and water reporting: who needs to report](https://www.ontario.ca/document/guide-energy-and-water-reporting/who-needs-report)
4.  [Guide to energy and water reporting: list of building types](https://www.ontario.ca/document/guide-energy-and-water-reporting/list-building-types)
5.  [Guide to energy and water reporting: who is exempt from reporting](https://www.ontario.ca/document/guide-energy-and-water-reporting/who-exempt-reporting)
6.  [Guide to energy and water reporting: what you are required to report](https://www.ontario.ca/document/guide-energy-and-water-reporting/what-you-are-required-report)
7.  [Guide to energy and water reporting: information you need for reporting](https://www.ontario.ca/document/guide-energy-and-water-reporting/information-you-need-reporting)
8.  [Guide to energy and water reporting: how to report](https://www.ontario.ca/document/guide-energy-and-water-reporting/how-report)
9.  [Guide to energy and water reporting: submit your report](https://www.ontario.ca/document/guide-energy-and-water-reporting/submit-your-report)
10.  [Guide to energy and water reporting: how EWRB uses building data](https://www.ontario.ca/document/guide-energy-and-water-reporting/how-ewrb-uses-building-data)
11.  [Ontario Data Catalogue: Energy and water usage of large buildings in Ontario](https://data.ontario.ca/dataset/energy-and-water-usage-of-large-buildings-in-ontario)
12.  [ENERGY STAR Portfolio Manager glossary](https://portfoliomanager.energystar.gov/pm/glossary)
13.  [Guide to submitting data through Portfolio Manager for EWRB](https://www.ontario.ca/page/submitting-data-through-portfolio-manager-ontarios-energy-and-water-reporting-and-benchmarking)

This guide is for orientation only and is not legal advice. Requirements depend on each building’s size, type and location, and programs change: confirm the details on the regulator’s own pages before you file.

## Related guides

-   Ontario
    
    ### [Whole-building data for Ontario EWRB: how to request it from each utility](https://brickflow.ca/guides/ontario-utility-data-requests)
    
    How to request aggregated whole-building electricity, gas and water data for Ontario EWRB from each utility, with forms, contacts and Green Button links.
    
-   City of Toronto
    
    ### [How to report energy and water use to the City of Toronto: a step-by-step guide](https://brickflow.ca/guides/toronto-energy-water-reporting)
    
    Who must report under Toronto Municipal Code Chapter 367, what is due when, and how to submit through Portfolio Manager, including the 2027 first-time cohort.
    
-   Canada and international
    
    ### [Data verification and assurance for building energy, water and emissions](https://brickflow.ca/guides/data-verification-and-assurance)
    
    What verification and limited or reasonable assurance mean for building energy, water and emissions data, who asks for them in Canada, and how to prepare.
    

## Keep every building ready before the deadline

BrickFlow keeps one reviewed record for each building, so the data for each program is complete and traceable when you file.