Canada and international

How to take part in the GRESB Real Estate Assessment: a step-by-step guide

On this page
  1. Who takes part and why
  2. What you need before you start
  3. Step by step
  4. Checks before you submit
  5. Verification
  6. After you submit
  7. Common mistakes
  8. How BrickFlow helps

GRESB runs an annual sustainability benchmark for real estate. Its Real Estate Assessment collects management and asset-level performance data from property companies, funds and developers, validates it, scores it against peers and gives the results to participants and, when they choose, to their investors. GRESB says more than 150 institutional and financial investors use it to monitor their managers. It is not a regulation: no law requires you to take part, but your investors may.

This guide is for owners, asset managers and sustainability leads at Canadian real estate companies and funds who have been asked to report to GRESB, or expect to be. It follows the reporting cycle in order, from deciding what you report to reading your results, and spends most of its time on the building data, because that is where most of the work and most of the points sit.

Who takes part and why

GRESB’s benchmark covers listed property companies, private property funds, developers and investors that invest directly in real estate. The unit that reports is an entity, usually a fund or a company, not a building. In the 2025 cycle, 1,002 fund managers submitted 2,382 assessments.

The usual reason to take part is that an investor or limited partner asks for a GRESB score, often as part of a mandate or fund agreement. Participants receive a scorecard, a benchmark report against a peer group, a portfolio analysis tool and a data exporter, and they decide whether to share their results with investors. First-time participants can choose a grace period and keep their results confidential for the first year.

The assessment has up to four components (Real Estate Assessment):

Component What it measures Who completes it
Management Strategy and leadership, policies and processes, risk management and stakeholder engagement, at the organization level Every participant
Performance Asset and portfolio performance: energy, GHG emissions, water, waste, building certifications Entities with standing (operating) investments
Development Sustainability during design, construction and major renovation Entities with development projects
Residential Additional residential indicators Entities with more than 75% residential assets by gross asset value

The 2025 scoring document sets the maximum at 100 points: Management 30 and Performance 70 for the Standing Investments benchmark, or Management 30 and Development 70 for the Development benchmark. GRESB’s 2026 scoring document was still marked “Under Development” on 9 October 2026, so where this guide describes scoring methods it relies on the 2025 document plus the 2026 point values.

GRESB does not publish its fees; its fee schedule page asks you to contact GRESB.

What you need before you start

Your reporting boundary

Decide which entity you are reporting, which of its assets are standing investments and which are developments, and which assets were bought or sold during the reporting years. GRESB says lack of operational control is not a valid reason to exclude an asset: where you do not control a space, you report what you know or disclose that the data is unavailable.

Asset characteristics

For each asset, the R1 asset characteristics indicator asks for:

  • the asset name and property sub-type;
  • country (ISO 3166 code), province and city, with the street address encouraged;
  • your percentage of ownership;
  • the purchase date (“Ownership From”) or sale date (“Ownership To”) if the asset changed hands;
  • gross floor area for the whole asset, regardless of your ownership share;
  • optionally, the construction year and gross asset value.

Do not invent your own asset ID. GRESB assigns it.

Two years of consumption, split by space

For energy, GHG, water and waste you report two consecutive years, for the whole space regardless of your ownership share. For each utility you also give the floor area the data covers and the maximum floor area that utility serves, and GRESB calculates coverage from those figures. Floor areas can be in m² or sq ft; water is in m³.

Where you can, split each asset into base building (common areas and shared services) and tenant space, and mark each tenant space as landlord-controlled or tenant-controlled. Report at whole-building level only when that split is not available. GRESB scores landlord- and tenant-controlled areas separately, and its aggregation handbook counts common areas, shared services and landlord-controlled tenant space as landlord-controlled.

GHG emissions are calculated by you, not by GRESB. You report them by scope, with location-based Scope 2 mandatory using the most relevant grid-average factor for the asset’s location. From 2026, emissions from landlord-controlled tenant space move out of Scope 3 into Scopes 1 and 2.

Tenant-controlled space is usually the hardest data to get. Start asking tenants for their consumption, or for authorization to obtain it, well before April.

Bringing Portfolio Manager data across

Many Canadian portfolios already keep monthly whole-building data in ENERGY STAR Portfolio Manager for Ontario EWRB, Toronto or other programs. That data is a good starting point, but it does not hold everything GRESB asks for, and GRESB’s Asset Portal guide lists only the Asset Spreadsheet, the Asset API and direct editing as ways to enter data. To bring it across:

  1. Export the monthly meter data for the two reporting years from Portfolio Manager.
  2. Tag each meter by the space it serves (common areas, shared services, landlord-controlled or tenant-controlled tenant space) and by utility type.
  3. Add what GRESB needs that Portfolio Manager does not hold: ownership share and dates, floor area covered and maximum floor area per utility, and the property sub-type.
  4. Enter the result in the GRESB Asset Spreadsheet layout and import it to the Asset Portal (step 5 below).

You can do this yourself, with your consultant, or with a data tool that produces the GRESB layout. Keep Portfolio Manager as the record your regulatory filings come from, so that the figures you send to GRESB and to regulators agree.

Step by step

  1. Talk to GRESB about membership. Ask about participation and fees through the participant membership page; fees are not published. Ask whether a first-year grace period suits you.
  2. Watch for the cycle to open. In 2026, the GRESB Portal opened on 1 April. On 9 October 2026 GRESB’s key dates page still shows the 2026 cycle only; the 2027 dates are not published, so check that page before you plan.
  3. Set up the entity and its components. In the GRESB Portal, describe the reporting entity and choose the components that apply to it, using the descriptions on the Real Estate Assessment page.
  4. Export the Asset Spreadsheet. In the Asset Portal, choose “Export Asset Spreadsheet”. A first-time reporter gets a blank file; a returning participant gets last year’s data pre-filled (Asset Portal guide).
  5. Fill in and import it. Complete the asset characteristics and the two years of consumption for each asset, then choose “Import”. Do not change asset IDs on existing assets, or you will create duplicates. The spreadsheet suits most portfolios; the Asset API is meant for portfolios of more than 2,000 assets, and direct editing for checks and small fixes.
  6. Handle sold assets correctly. Do not delete them. Enter the sale date in “Ownership Until”; sold assets stay visible but are left out of aggregation and validation.
  7. Apply estimation rules only where allowed. Estimates may fill gaps in partly available data, up to 20% of the period with actual data and three months across both years, using data of the same type. Disclose the method, the estimated share and the reason in the text box under each indicator.
  8. Complete the Management and, if it applies, Development components. Answer each indicator and attach evidence where it asks for it, following the indicator guidance in the 2026 Real Estate Assessment guides.
  9. Answer MR1 to MR4. Say whether your energy, GHG, water and waste data was externally checked, verified or assured, and upload the evidence (see Verification).
  10. Consider a Pre-Submission Check. In 2026 these could be requested from 1 April and performed until 20 June. Ask GRESB what the check covers for your entity.
  11. Re-aggregate. The Performance component does not update itself from the Asset Portal. GRESB strongly recommends re-aggregating as the last step before you submit.
  12. Submit by the deadline. In 2026 the portal closed on 1 July at 23:59 PDT. Leave time to fix import errors before the deadline.

Checks before you submit

  • Every asset in the boundary is in the Asset Portal, with sold and bought assets dated, not deleted.
  • Gross floor area is for the whole asset, not your share, and matches last year unless something physical changed.
  • Floor area covered never exceeds maximum floor area, and an asset with no known consumption shows 0 covered.
  • Both years are complete for each meter. GRESB’s like-for-like method in the 2025 scoring document only counts assets with more than 355 days of data and the same coverage, within 1%, in both years.
  • Units are right: natural gas bought in m³ is converted to energy, water is in m³, and each floor area is in the unit the spreadsheet column expects.
  • Estimates follow the estimation rules and are disclosed.
  • Location-based Scope 2 is reported for every asset with purchased electricity.
  • The MR evidence covers the same data, years and assets you reported.
  • The response has been re-aggregated since the last import.

Verification

GRESB does not require external review of your data, but it scores it. Indicators MR1 to MR4 cover external review of energy (1.75 points), GHG (1.25), water (1.25) and waste (1.25) data, 5.5 points in total in the 2026 scoring document.

For each, you choose the highest level of review the data received (MR1 guidance):

Option What it means Share of the indicator’s points
Externally checked Reviewed in a structured and consistent process, without an official certification One third
Externally verified Reviewed against an existing scheme, which you name Full
Externally assured Reviewed against an existing scheme, which you name Full

The shares come from the 2026 scoring document. GRESB treats verification and assurance equally and validates the evidence by hand: accepted evidence keeps the full score, partly accepted evidence keeps a third, and rejected evidence scores nothing. The evidence must show the review exists and covers the data you reported, state the type of review and any standard used, and show the reviewer is an independent third party. If this is your first review, GRESB accepts a confirmation from the auditor that the work is in progress.

GRESB keeps a list of recognized schemes. It includes ISO 14064-3, ISAE 3000, ISAE 3410, ISSA 5000, the AA1000 Assurance Standard and, for Canada, CSAE 3000 and the older CICA Handbook Assurance Section 5025. CSAE 3410 and CSSA 5000 are not on the list, so confirm with GRESB before you rely on either. New schemes must be submitted to GRESB by 15 March to be reviewed that year.

Book your provider early: the review has to finish before the 1 July deadline, and the same provider may also be doing your Ontario EWRB verification. For the difference between internal review, verification and assurance, and how to prepare for an engagement, see Data verification and assurance.

After you submit

  • Validation. GRESB checks data points automatically and reviews evidence documents with human reviewers and automated tools. In 2026, validation started in August.
  • Peer group. In 2026 real estate participants could customize their peer group from 20 July to 15 August.
  • Preliminary results and correction. Preliminary results went to participants on 1 September 2026, followed by an Assessment Correction period from 1 to 15 September to respond to flagged issues and amend data.
  • Final results. Results reached participants and investors on 1 October 2026 from 09:00 UTC. You then decide what to share with your investors.
  • Results review. From 1 October you can request a Results Performance Review; the page gives 30 January as the last day.
  • Next year. Your Asset Portal data carries forward, and this year’s second year becomes next year’s first. Fix any gaps now so the next export starts clean.

Common mistakes

  • Reporting your share instead of the whole asset. GRESB wants gross floor area and consumption for the whole space; your ownership percentage is a separate field.
  • Deleting sold assets. Enter the sale date instead.
  • Leaving out tenant-controlled space. No operational control is not a reason to exclude it. Report what you know, or disclose that it is unavailable.
  • Sending Portfolio Manager totals as they are. Portfolio Manager does not hold ownership, floor area covered or control type, so add them, and the space split where you have it, before you import.
  • Estimating outside the rules. Using last year’s data, area averages or generic benchmarks to fill a gap is not allowed; if you cannot follow the rules, you report 0% coverage for that data.
  • Coverage that changes between years without a reason. It can drop an asset out of like-for-like.
  • Evidence that does not match. An assurance statement for a different year, entity or set of assets will be partly accepted or rejected.
  • Choosing an unrecognized scheme. Check the scheme list before you engage a provider.
  • Forgetting to re-aggregate. Imports after your last aggregation do not reach the Performance component.

How BrickFlow helps

BrickFlow keeps one reviewed record per building: floor area with its source, ownership, every meter tagged by the space it serves and who controls it, and two years of usage from Green Button data and the bills and files you provide. It exports energy, water and emissions figures in GRESB’s own spreadsheet layout, from the same record your Portfolio Manager filings use. Our own review flags gaps, overlaps and unit errors before you import; it is not the external review that MR1 to MR4 score, but it keeps the documents your verifier or assurance provider will ask for in one place.

Sources

  1. GRESB: Real Estate Assessment
  2. GRESB: Participant membership
  3. GRESB: Key dates, 2026 reporting cycle
  4. GRESB: Annual fee schedule
  5. GRESB: 2025 Real Estate scoring document
  6. GRESB: 2026 Real Estate scoring document (under development)
  7. GRESB: R1 Asset characteristics (2026)
  8. GRESB: WT1 Water consumption (2026)
  9. GRESB: GH1 Scope 1-3 emissions (2026)
  10. GRESB: Energy aspect (2026)
  11. GRESB: Aggregation handbook
  12. GRESB: Asset Portal guide
  13. GRESB: 2026 Real Estate Assessment guides
  14. GRESB: Data estimation rules (2026)
  15. GRESB: Data quality and validation (2026)
  16. GRESB: MR1 External review of energy data (2026)
  17. GRESB: Assurance and verification schemes

This guide is for orientation only and is not legal advice. Requirements depend on each building’s size, type and location, and programs change: confirm the details on the regulator’s own pages before you file.

Keep every building ready before the deadline

BrickFlow keeps one reviewed record for each building, so the data for each program is complete and traceable when you file.