Quebec now requires the owners of large buildings to declare their buildings’ energy use to the province every year. The government’s page calls it the mandatory declaration of the energy consumption of large buildings. The rules are in the Regulation respecting the mandatory declaration of the environmental performance of certain buildings (in French), published in the Gazette officielle on 23 June 2026 and in force on the fifteenth day after publication (article 25). It is made under the Act respecting the environmental performance of buildings, and is administered by Quebec’s environment ministry, the Ministère de l’Environnement, de la Lutte contre les changements climatiques, de la Faune et des Parcs.
This guide is for owners, property managers, syndicates of co-owners and consultants with commercial, multi-residential, institutional or mixed-use buildings in Quebec. The first declaration is due by 30 June 2027 and must include monthly data for 2025 and 2026, so the work starts now. The ministry’s filing platform is not open yet; this guide covers what you can confirm and prepare today, and we will update it when the ministry publishes the platform’s instructions.
Does it apply to you?
Under article 3 of the regulation, the obligation applies in two phases.
| Obligation applies from | Buildings covered |
|---|---|
| 1 January 2027 | Buildings of at least 5,000 m² of total floor area, except exclusively residential buildings; residential or partly residential buildings with at least 50 dwelling units; buildings owned by a public body other than a municipal body, with an exception for buildings under 100 m² |
| 1 January 2028 | Buildings of at least 2,000 m² of total floor area, except exclusively residential buildings; residential or partly residential buildings with at least 25 dwelling units |
The quebec.ca page summarizes the first phase as commercial and municipal buildings of 5,000 m² and more, buildings with 50 or more units, and State buildings over 100 m². Its examples of covered buildings are a 6,000 m² shopping centre, a 5,500 m² office building, a 60-unit residential building, and a school or government building of 1,500 m². A 22-unit residential building is not covered, even if it is larger than 2,000 m². A public body has the meaning given in Quebec’s access to information act (section 2 of the Act). If you own small public-body buildings, read the exact wording of article 3 or ask the ministry.
Declarations are due by 30 June of each year after the obligation starts (article 3), so buildings covered from 2028 make their first declaration by 30 June 2028.
Total floor area is measured from the outer face of the exterior walls and excludes crawl spaces and partly open spaces. For semi-detached or attached buildings, the property line counts as the exterior wall (article 3).
Who files
Article 2 names the person responsible:
- the owner, where one owner holds the building;
- the syndicate of co-owners, for a building in divided co-ownership (a condominium);
- each co-owner, for a building in undivided co-ownership, unless the co-owners designate one of them to file (article 6);
- the emphyteutic lessee, for a building held under emphyteusis.
Exclusions
Article 1 excludes buildings that are under construction; covered by a demolition permit the owner has obtained; on the site of a manufacturing establishment (NAICS 31-33), a mining establishment (NAICS 21) or a water, sewer or related system (NAICS 2213); mainly used for agriculture; or used to maintain, store or operate a metro, including metro stations.
What you need before you start
The declaration’s content is set by articles 4 and 5. For each building, gather:
- Owner details. Name and contact details of the owner and their representative (and of the designated undivided co-owner, if any), the Quebec enterprise number if the owner is registered, and whether the building is held in divided or undivided co-ownership or under emphyteusis.
- Building details. Address, year built, total floor area, each use type with the floor area it occupies, the number of dwelling units if the building is wholly or partly residential, and whether it is a heritage building listed under section 8 of the Act.
- Energy bought from a distributor. Quantities and costs for each source and billing period: electricity, renewable natural gas, natural gas, and steam, hot water or chilled water from a district network. Quebec.ca describes this as monthly data.
- Two calendar years for the first declaration. The first declaration covers the two previous calendar years (2025 and 2026 for a declaration due in 2027); later declarations cover the previous calendar year.
- Peak demand. Where you report electricity, the maximum power demand documented by your electricity distributor.
- Delivered fuels. Quantities, types, delivery dates and costs of liquid biofuels (such as biodiesel), solid biofuels (such as wood and wood-residue products), diesel, heating oil and propane, including renewable propane.
- District energy details. If you buy steam, hot water or chilled water, the supplier’s name and its greenhouse gas emission factor.
- Renewables. Proof that purchased energy is 100% renewable, if that applies, and the quantity of energy the building uses from on-site renewable production.
You may leave out energy used for vehicle charging, industrial processes, telecommunications antennas, or heating, ventilating or lighting a greenhouse, but only where a meter measures that use separately (article 5).
Data from your distributors. By 31 December 2026, your electricity distributor and your natural gas distributor must each run a digital platform that transfers your building’s consumption, total costs and peak demand to you. For a building with several meters for one source, the transfer gives monthly totals across those meters (articles 12 and 13). Delivered fuels are not covered by these platforms, so keep your delivery invoices.
Step by step
The ministry’s platform opens in early 2027, and its screen-by-screen steps are not published yet. Steps 1 to 5 follow the preparation steps on the quebec.ca page; steps 6 to 9 follow the regulation.
- Check whether each building is covered. Compare floor area, unit count, ownership and use against the list of covered buildings and the exclusions in article 1. Note which year the obligation starts for each building.
- Gather the building information. Collect the owner, building and floor area details listed above (quebec.ca).
- Choose a compatible tool. Quebec.ca lists three tools compatible with the future platform: ENERGY STAR Portfolio Manager, Hélios (for institutional clients) and an Excel collection template, which is still to come (quebec.ca). Portfolio Manager is one option, not a requirement. To use it, create a free account.
- Track the building’s energy in that tool. Set up the building and a meter for every source, and enter 2025 and 2026 quantities and costs by billing period, including delivered fuels and district energy (quebec.ca).
- Authorize your distributors to transfer data, if you use Portfolio Manager. Quebec.ca recommends authorizing your distributor to send your building’s consumption data to Portfolio Manager automatically, so you do not enter it by hand at declaration time. It links to the instructions of the electricity and natural gas distributors, and says an option for one of the gas distributors will be offered soon (quebec.ca).
- Plan the verification. Decide in which year of the four-year period your declaration will be verified, and engage a member of one of the six orders listed below (article 9).
- File on the ministry’s platform. Use the declaration platform available from the ministry’s website (article 3). If several of your buildings are physically linked, or are not metered separately, you may file one declaration for them, with floor area that includes enclosed walkways and corridors between them (article 7).
- Attach the verification report, in a verification year. The report goes with the declaration (article 9).
- Submit by 30 June. If you acquired the building less than 90 days before 30 June, the deadline is 30 September of the year of acquisition (article 3).
Quebec.ca says guides and support tools will be published to help with the declaration, and offers a newsletter for updates.
Checks before you file
- Every source the building uses is included: electricity, natural gas and renewable gas, district energy, and delivered fuels such as heating oil, propane, diesel and wood.
- Each source covers every billing period of both calendar years in a first declaration, with no gaps or overlapping bills.
- Costs are entered with quantities; the regulation asks for both.
- Total floor area follows the regulation’s definition, and the floor areas by use add up to the total.
- Units match the bill for each meter: kWh for electricity, m³ for natural gas, and the unit on the delivery invoice for heating oil, propane and other delivered fuels.
- Any energy you excluded (vehicle charging, process, antennas, greenhouses) is separately metered.
- Distributor data transferred into your tool matches your bills for the same periods, and no supply is entered twice.
- In a verification year, the verification report covers the period you are declaring.
Verification
Under article 9 of the regulation, you must have the content of your declaration verified at least once in each four-year period following the date the obligation starts to apply to your building. The verification report is attached to the declaration. The regulation does not say which declaration within the period must be verified, so confirm your timing with the ministry before you plan.
Who can verify. A member of one of these professional orders (article 10):
- Ordre des administrateurs agréés du Québec
- Ordre des architectes du Québec
- Ordre des comptables professionnels agréés du Québec
- Ordre des évaluateurs agréés du Québec
- Ordre des ingénieurs du Québec
- Ordre des technologues professionnels du Québec
The verifier cannot be the owner, or the person the owner designated to prepare the declaration being verified.
What the report contains. The verifier’s name, professional contact details and order membership number; their employer, if any; the owner’s name and contact details; the period verified and the documents consulted; and the professional’s statement on the validity of the data the owner declared (article 11).
When a building changes hands. A new owner does not need a new verification for a period already covered by a verification report (article 9).
For how verification differs from internal review and from assurance, see Data verification and assurance.
After you file
- Keep your records for seven years. Keep every document supporting your declaration for 7 years from the date of the declaration, and provide it to the ministry on request within the time it sets (article 8).
- Declare again each year. After the first declaration, each one covers the previous calendar year (article 5).
- Public register. The Act requires the minister to keep a public register of building environmental performance (section 17), with contents to be set by a government regulation. The declaration regulation does not set those contents, so what will be published is not yet known. Section 17 withholds the addresses of shelters for victims of violence, and an owner’s name and address where the owner asks because access could endanger their safety or an occupant’s.
- Ratings come later. The Act provides for an environmental performance rating to be set by government regulation (sections 5 and 6), and the ministry says the data it collects will help prepare the rating system. No rating regulation has been published.
- Penalties. The regulation sets administrative monetary penalties and fines (articles 19 to 24):
| Breach | Administrative monetary penalty (individual / other) | Fine (individual / other) |
|---|---|---|
| Not keeping supporting documents, or not providing them on request | $250 / $1,000 | $1,000 to $100,000 / $3,000 to $600,000 |
| Not filing the declaration, or not having it verified or not attaching the report | $500 / $2,500 | $2,500 to $250,000 / $7,500 to $1,500,000 |
| Providing false or incomplete information | $1,000 / $5,000 | $5,000 to $500,000 / $15,000 to $3,000,000 |
- In Montréal, report to the City as well. Montréal’s By-law 21-042 is a separate obligation: buildings of 2,000 m² or more, or with 25 or more dwellings, report their greenhouse gas emissions to the City by 30 June each year through Portfolio Manager.
- Questions: [email protected] (quebec.ca).
Common mistakes
- Starting in 2027. The first declaration needs billing-period data for 2025 and 2026. Bills that are hard to find now will be harder to find next spring.
- Missing delivered fuels. Heating oil, propane, diesel for generators and wood arrive on delivery invoices, not on a monthly bill, and the distributor platforms do not cover them.
- Leaving out tenant-metered supply. Article 5 asks for the energy the building consumes, and the distributor platforms under article 13 total all of a building’s meters. If you are unsure how tenant accounts are treated, ask the ministry.
- Using the wrong floor area. Rentable area or a marketing figure is not total floor area as the regulation defines it, and floor area decides whether the building is covered at all.
- Excluding loads that are not separately metered. Vehicle charging and the other permitted exclusions apply only where a meter measures them.
- Booking the verifier too late. Only members of six orders can verify, and the person who prepared the declaration cannot. Leave time before 30 June to correct findings.
How BrickFlow helps
BrickFlow keeps one reviewed record per building: total floor area with its source, every meter and delivered fuel, and quantities and costs by billing period, brought in from Green Button data and the bills and files you provide. Our own review flags gaps, overlaps, unit errors and duplicate meters before you enter the data in your compatible tool, and keeps the supporting documents in one place for the seven years the regulation requires. That review is not the verification the regulation requires; it gives the professional you engage an organized record to work from.
Sources
- Québec.ca: Déclaration obligatoire de la consommation énergétique des grands bâtiments (updated 25 June 2026)
- Gazette officielle du Québec, 23 June 2026: Règlement sur la déclaration obligatoire de la performance environnementale de certains bâtiments
- LégisQuébec: Act respecting the environmental performance of buildings (P-9.02), up to date 12 August 2026
- ENERGY STAR Portfolio Manager: sign in or create an account
- Québec.ca: Déclaration des distributeurs d'énergie (updated 21 August 2026)
- Ville de Montréal: Law concerning GHG emission disclosures and ratings of large buildings
This guide is for orientation only and is not legal advice. Requirements depend on each building’s size, type and location, and programs change: confirm the details on the regulator’s own pages before you file.